1001 106th Ave NE
March 3, 2008:
Hanover Bellevue Cadillac Site - Phase 1 & 2. Proposed demo of an existing auto dealership to construct two, 20 story high rise apartment buildings with commercial in two phases. Phase I (westerly tower): 1 level of underground parking with 3.5 partial levels of above grade parking embedded within one 20 story tower. Phase II (easterly tower): two levels of underground parking with 2.5 partial levels of above grade parking embedded within one 20 story tower. An urban plaza to be provided at the SE corner of site with Phase II. Binding Site Plan included with this decision.
Dec. 4, 2008: Completed.