Seattle in Progress

Seattle in Progress

About Calendar Upgrade to Pro Sign In
  • About
  • Calendar
  • Upgrade to Pro
  • Sign In

1001 106th Ave NE

March 3, 2008: Hanover Bellevue Cadillac Site - Phase 1 & 2. Proposed demo of an existing auto dealership to construct two, 20 story high rise apartment buildings with commercial in two phases. Phase I (westerly tower): 1 level of underground parking with 3.5 partial levels of above grade parking embedded within one 20 story tower. Phase II (easterly tower): two levels of underground parking with 2.5 partial levels of above grade parking embedded within one 20 story tower. An urban plaza to be provided at the SE corner of site with Phase II. Binding Site Plan included with this decision.

Dec. 4, 2008: Completed.

Start a free trial of our Pro Subscription to see additional project details, contact information, permit schedules and more.

Sign up for free calendar updates over email

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.

Filter by Project Status
Filter by Project Type

Start a free trial of our Pro Subscription to search by project type, size, permitting status, architect, developer and more.