910 128th Ave SE
April 3, 2008: Lake Hills Connector to NE 10th Street PSE Gas Main. Installation of 3.5 miles of new natural gas distribution main within City of Bellevue public Right-of-Way between an existing main located in 140th Ave SE and an existing distribution system district regulator located on the north side of NE 10th Street, approximately mid-block between 108th Ave NE and 110th Ave NE. The installation will be completed via open trenching, horizontal directional drilling and boring.
July 25, 2008: Completed.
Start a free trial of our Pro Subscription to see additional project details, contact information, permit schedules and more.
Sign up for free calendar updates over email
Start a free trial of our Pro Subscription to search by project type, size, permitting status, architect, developer and more.