3226 W Lake Sammamish Pkwy SE

March 16, 2015: Pier Reconfiguration. Add platform to pier. Remove every other set of 4x4 piles and caps (30 piles & 12 caps.) Sleeve remaining 4x4 files with HDPE pipe and fill with concrete. Repair caps and stringers. Replace decking with Titan grated decking.

Oct. 14, 2015: Completed.