148 W Lake Sammamish Pkwy SE
Jan. 21, 2020: Nann pier repair and platform lift. Repair piles as needed by sleeving with HDPE pipe and filling with concrete. Repair caps and stringers. Replace decking with Titan grated decking. Remove rail system. Remove 1 mooring pile. Remove fingers of the slip (78.5 SF) and four associated support piles. Remove the attached 220 SF canopy of the existing boatlift. Install a fully grated platform lift.
Oct. 21, 2020: Completed.