701 Shoreland Dr SE

April 14, 2020: Bryant Pier. *19-131102 EA* We propose to demo existing mooring piles and replace decking material with Thruflow grated decking. We will also install a 10ft extension w/(2) new 8" wood piles, Installing a new finger w/(6) new 8" wood piles & install (2) new 10" steel mooring piles; We will repair (11) piles and replace (1) pile;

Feb. 18, 2021: Completed.